The Cornelius Pass Road Pipeline Project (PLW_2.0) is a 3.3-mile section of pipeline between Frances Street and the Tualatin Valley Water District connection point just south of Highway 26. About 900 feet of this section of the pipeline will cross the northeast corner of Orenco Woods Nature Park (OWNP).

Cornelius Pass Road Pipeline Anticipated Project Timeline

  • Meet the Contractor Event: November 2022
  • First OWNP Wildlife Management Quarterly Meeting: November 2022
  • Initial Construction Mobilization: November 2022
  • Pipeline installation through OWNP and old rail corridor completion: October 2024