The Metzger Pipeline East (MPE_1.0) merges already planned construction by the Tualatin Valley Water District (TVWD) into ongoing plans for the Willamette Water Supply System and the City of Beaverton. The project more efficiently utilizes TVWD and City of Beaverton infrastructure to maximize cost-effectiveness and reduce community and environmental impacts from construction.

The project enhances the reliability and seismic resiliency of drinking water service for City of Beaverton and Tualatin Valley Water District (TVWD) customers. Construction of this new system provides jobs and benefits the local economy today and is designed to withstand a large earthquake or other natural disaster so that water service can be restored quickly and our communities can recover sooner.

Those living, traveling, working, and shopping along portions of SW Scholls Ferry Road, SW Hall Boulevard, SW Cascade Avenue, SW Allen Boulevard and Western Avenue can expect various construction activities from the fall of 2021 until the fall of 2024.

UPDATES

Current Traffic Impacts

  • Westside Regional Trail and sidewalk at Scholls Ferry Rd closure--Began 7/19, M-F closure from 7 am to 4 pm (flyer)
  • Allen Blvd-- intermittent road maintenance. Daytime work, M-F, 7 am to 4 pm
  • Intermittent Nightwork--Scholls Ferry Rd from Conestoga Dr to 135th Ave, 7 pm to 5 am. The activities are scheduled to last through July. Crews are working one area at a time at multiple locations generally 2-4 days at each for the work.  Crews will remain near Conestoga into the week 7/29.  (flyer)
  • Scholls Ferry Rd, Snowgoose Ln to Teal Blvd. Day work with some night work for intersections with traffic signals. One daytime crew is working westward from Blackbird Dr/158th Ave and one daytime crew is working eastward near the Westside Regional Trial. (flyer)
  • Scholls Ferry Rd, Roy Rogers Blvd to Murray Blvd. Daytime work, M-F, 7 am to 4 pm (flyer)

Upcoming Traffic Impacts

  • Intermittent Daywork, Scholls Ferry Rd from 135th Ave to Murray Blvd. Activities are scheduled to begin in Aug. Crews are working one area at a time at multiple locations generally 2-4 days at each.
  • Nightwork, Scholls Ferry Rd at Teal Blvd. Tentatively begins Aug 12th
  • Nightwork, Scholls Ferry Rd at Barrows Rd. Tentatively begins in Aug 26th
  • Allen Blvd road restoration. TBD
  • Nightwork, Scholls Ferry Rd at Roy Rogers Rd. Tentatively Sept/Oct