wwsp-mpe-traffic-updates-road-work-1200px

Following an especially rainy spring, the Willamette Water Supply Program has changed the construction schedule for installation of an underground water pipeline through Wilsonville.

With the end goal of building an underground pipeline from Southwest Wilsonville Road to Southwest Garden Acres Road, construction began on Southwest Kinsman Road in February, but crews were met with high levels of groundwater that made work in the area difficult.

As a result, construction on that portion of the pipeline has been postponed to August, and work on a section of the pipeline that will run along Southwest 95th Avenue from Hillman Court to Ridder Road will begin this month instead.

Read the article here. Wilsonville Spokesman, Kaelyn Cassidy, April 7, 2023