The Cornelius Pass Road Pipeline Project (PLW_2.0) is a 3.3-mile section of pipeline between Frances Street and the Tualatin Valley Water District connection point just south of Highway 26. About 900 feet of this section of the pipeline crosses the northeast corner of Orenco Woods Nature Park (OWNP).
Project Update: Completion Timeline (formerly anticipated milestones)
Construction of the Cornelius Pass Road Pipeline Project was delayed in early 2023 due to supply chain issues that affected the availability of long lead items necessary for construction. Despite these challenges, construction has been completed.
- Initial Construction Mobilization: Early 2023
- Pipeline installation through OWNP completed: June 2024
- Pipeline installation through old rail corridor completed: Fall 2024
Wildlife Management Plan Stakeholder Meeting #8
The eighth OWNP Wildlife Management Public Meeting was held online (Zoom) on November 6, 2024. The meeting was recorded and is now available for viewing below.